Stormwater Pollution Prevention Plan (SWPPP) for Coal Storage Area Stabilization Project [electronic resource]

 0 Người đánh giá. Xếp hạng trung bình 0

Tác giả:

Ngôn ngữ: eng

Ký hiệu phân loại: 629.2 Motor land vehicles, cycles

Thông tin xuất bản: Washington, D.C : Oak Ridge, Tenn. : United States. Dept. of Energy. Office of the Assistant Secretary for Defense Programs ; Distributed by the Office of Scientific and Technical Information, U.S. Dept. of Energy, 2011

Mô tả vật lý: Medium: ED : , digital, PDF file.

Bộ sưu tập: Metadata

ID: 268520

 The scope of this project is to stabilize the abandoned coal storage area and redirect the storm water runoff from sanitary sewer system to the storm drain system. Currently, the existing storm water runoff is directed to a perimeter concrete drainage swale and collected in a containment basin. The collected water is then pumped to a treatment facility and after treatment, is discharged to the Y-12 sanitary sewer system. The existing drainage swale and collection basin along with silt fencing will be used during aggregate placement and grading to provide erosion and sediment control. Inlet protection will also be installed around existing structures during the storm water diversion construction. This project scope will include the installation of a non-woven geotextile fabric and compacted mineral aggregate base (paving optional) to stabilize the site. The geotextile specifications are provided on the vendor cut sheets in Appendix B. The installation of a storm water collection/retention area will also be installed on the southern side of the site in accordance with EPA Technical Guidance on Implementing the Stormwater Runoff Requirements for federal Projects under Section 438 of the Energy Independence and Security Act. The total area to be disturbed is approximately 2.5 acres. The order of activities for this Stormwater Pollution Prevention Plan (SWPPP) will be: (1) post notice of coverage (NOC) in a prominent display near entrance of the site
  (2) install rain gauge on site or contact Y-12 Plant Shift Superintendent daily for Met tower rain gauge readings
  (3) install stabilized construction exit on site
  (4) install silt fencing along perimeter as indicated on the attached site plan
  (5) regrade site
  (6) install geotextile fabric and compacted mineral aggregate base
  (7) install catch basin inlet protection where required
  (8) excavate and lower existing catch basin tops, re-grade and asphalt to drain
  and (9) when all disturbed areas are re-stabilized, remove silt fencing and any other temporary erosion control.