Abstract: Delayed site clearance poses a significant challenge in transportation construction investments nationwide. It results in project operational delays, increased investment costs due to extended construction timelines, and necessitates adjustments that inflate total investment, thereby diminishing project efficiency. This study delves into the underlying causes of sluggish site clearance and proposes solutions. Through surveys conducted with experts and professionals from various agencies and organizations, including investors, project management boards, consultants, and construction contractors, the study identifies experience in organizing and executing site clearance as the primary factor. Finally, the study presents three solutions aimed at improving land clearance progress for transportation construction investment projects in Can Tho City, based on the analysis and evaluation findings.Tóm tắt: Chậm giải phóng mặt bằng (GPMB) là một vấn đề quan trọng trong các dự án đầu tư xây dựng công trình giao thông, gây ra nhiều hệ lụy như chậm đưa công trình vào khai thác sử dụng, tăng chi phí đầu tư do kéo dài thời gian thi công, phải điều chỉnh tăng tổng mức đầu tư dẫn đến giảm hiệu quả đầu tư dự án. Nghiên cứu này tập trung tìm hiểu sâu các yếu tố gây ra chậm GPMB và đề xuất một số giải pháp khắc phục. Bằng phương pháp khảo sát chuyên gia và cá nhân làm việc ở các đơn vị là chủ đầu tư/ ban quản lý dự án, tư vấn và nhà thầu thi công, nghiên cứu xác định được nhân tố đánh giá cao nhất đó là kinh nghiệm tổ chức thực hiện. Nghiên cứu cũng đề xuất 3 giải pháp cải tiến tiến độ thực hiện GPMB dự án đầu tư xây dựng công trình giao thông trên địa bàn TP. Cần Thơ dựa trên kết quả phân tích và đánh giá.